Kitchen Remodel Update: Cabinets

Houston, we have cabinets. The countertops get measured tomorrow, and I have a punch walk with the production manager from the company that sold and installed the cabinets. At least one door will need to be replaced, and many of the shelves were 1/4" short and will be replaced. All free of charge, of course. The installers took three days to complete the work. I have never seen anybody work so meticulously as the two men who did the installation. Really exceptional work.

Appliances get delivered tomorrow, and the tile floor installation begins on Monday. By the end of next week, we should have appliances in place and functioning. Just no sink yet. We’re still on track for our December 1 completion date.

H/T to Oppo for helping with the drawer pull placement.